The Old Saltleians RFC training ground development is progressing at a pace, with the steel frame for the new clubhouse taking shape this week and completed ahead of programme, providing a great start for the building works.
Since starting on site in November 2021 we have completed the cut and fill works, earthworks, the foundations for the building and under the guidance of ecologists, the works to the existing pond and a new pond has been formed on site.
Whilst the weather over the last few months has created challenges, these have been overcome to keep the programme on schedule.
Keeping it Local and Recycling
To date we have brought to site over five thousand tonnes of recycled material avoiding the use of primary aggregates and recycled material has been sourced locally to reduce transport distance and impact on road users and the environment.
Materials were used to create the access road onto site as the first operation to provide access for construction works and avoid carrying debris onto the surrounding roads.
We are providing local staff resources for this project, achieving reduced travel times to site, meaning a decrease in travel time for staff, contributing towards reducing our emissions.
Community Relations
Fundamental to the success of the project is our ability to minimise impact and disruption to the local environment given the site’s location within a busy residential area with housing adjacent to the site.
Keeping residents informed is important and with this in mind a pre-start meeting was held with the local parish councillors and letter drops conducted to keep residents up to date on the works.
No complaints have been received.
Old Salteians RFC Project Overview
Works commenced on the project with a formal ground-breaking ceremony on 25 November 2021, for a 12-month duration to deliver a fantastic new facility for Old Saltleians, who are relocating due to HS2.
O’Brien are using our in-house civil engineering & construction expertise, along with our extensive sports development experience, delivering a turnkey design & build solution for the client.
The scheme includes a brand-new club house, associated access roads, car parks along with seven natural turf pitches and associated infrastructure. This will be a fantastic development for the club, the rugby, and local communities for generations to come.
The scheme follows on from our hugely successful scheme at Aston Villa training ground, which has been testament to our skills and capabilities when it comes to providing outstanding turnkey sports facilities.