Barry Callebaut, World’s Leading Chocolate Manufacturer, Major Works Project Progressing Well!

Building Alteration and Upgrading Works for New Tank Farm Installation

Our multi million pound contract at the Barry Callebaut factory, Banbury is progressing at a pace.  The works which are to allow the client to increase their production by circa 20%,  started in November 2019, with major alteration works on the new ‘Tank Farm Building’ completed.  The works on this building have been carried out to ensure that the building is ready for the new product tanks to be installed within the building.

Our works on this building have included:

  • Piling installation in the floor of the building to take the load imposed from the new product tanks to be installed
  • Concrete reinstatement – reinstate around piles
  • New resin floor installation
  • White walling to stop any contamination of the product
  • Installation of new steels – these were installed to strengthen the building, and for crane beams
  • Painting and decoration of the building
  • Brick up old roller shutter doors openings

Tank Farm Delivery Yard Construction

We have also constructed a new yard around the side and the rear of the ‘Tank Farm Building’ which was previously a landscaped area.  The new side access and new yard will allow deliveries to the rear of the building.  Our works have included:

  • Reduced dig around the side and to the rear
  • Muck shift
  • Installation of all drainage and ducting for the building
  • Install Hauraton channels and kerbs
  • Install concrete bases for canopy for the delivery area to the rear
  • Stone up
  • Concrete bays for the vehicle delivery area.

Future works to the yard area for the ‘Tank Farm’ include the installation of 3 no doc levellers at low level, installation of all new doors and windows for the doc levellers and installation of a building for the janitors, and installation of steel for the canopy.

Building Extension and Construction Works

Our works will be continuing on site until late 2020 with further works including building extension works, internal access roads and construction of a brand new 40m x 13m stand alone Utilities / Energy Centre.

Live Manufacturing Environment

All works are being carried out within a live manufacturing environment with a busy delivery and loading operation on the site.  O’Brien have a carefully controlled regime and works phasing to ensure that manufacturing and deliveries on site are uninterrupted.  Health and Safety standards are stringent to reflect both O’Brien and Barry Callebaut’s standards.

150 Year Old – World Leading of Manufacturer of High Quality Chocolate and Cocoa Products

Barry Callebaut is the world’s leading manufacturer of high-quality chocolate and cocoa products, and has been dedicated to this business for more than 150 years. The company operates out of more than 40 countries, runs about 60 production facilities, employs a global workforce of more than 12,000 people.

One in Four Chocolate & Cocoa Products Around the World Contain Barry Callebaut Products

With average sales of 2,139,758 tonnes of chocolate and cocoa products (2018/19), their products are present in one out of four of all chocolate and cocoa products consumed around the world.

The works are taking place under a 12 month programme of works.

When Central News Came to Our Dudley Project!

Work to extend the West Midlands tram network to Dudley has begun and Yasmin Bodalbhai the Central News reporter came to our site on 30 January 2020, to see how works were progressing. The works which are being carried out for Dudley Metropolitan Borough Council are in preparation for the proposed construction of the Very Light Railway Innovation Centre to allow for the future alignment of the Metro Line.

https://twitter.com/InsideOBrien/status/1222797509501890560?s=20

The Midland Metro, which currently connects Birmingham and Wolverhampton, is expected to carry passengers to Dudley and Brierley Hill by 2023.  The West Midlands Combined Authority (WMCA) said the tram line will “transform Dudley”, with council leader Pat Harley saying it “promises an exciting future” for the town. The new tram network will run from Dudley to Wednesbury, incorporating 17 stops.

West Midlands Mayor Andy Street said the success of town centres like Dudley will “hinge on transport links”.  “It is great to see work progressing on the Wednesbury to Brierley Hill Metro line, helping to better connect the borough of Dudley with the wider West Midlands,” he said.

The tram extension in Birmingham opened from Grand Central station to the city’s library in December, and a busy city-centre underpass was closed to extend the line towards Edgbaston.

The first phase of the project is to construct a £4.3m wall at Castle Hill.

O’Brien Contractors have been awarded an enabling contract on the project in Dudley next to the zoo and our works involve the construction of a 150 metre long retaining wall which will be up to 11 metres high and will also involve associated bulk earthworks.

O’Brien will be acting as Principal Contractor on the project which will be carried out over a 35 week programme.

The client was looking for a contractor who could deliver creative solutions to provide an affordable scheme in line with their programme.  The client also required a company with a robust supply chain procurement.

Having traded for over 60 years we have developed our supply chain to provide our business with the service required to meet our commitments to our clients. With long term trading relationships with suppliers of construction materials, aggregates, concrete, muckaway and recycling companies, we are able to select the most suitable option for each specific contract and operation which may not always be based on price, factors such as quality and performance also need to be considered.

O’Brien and the Next Generation of Construction Workers – 2019 Placements

O’Brien Contractors are very passionate about giving new generations of construction workers the opportunity to spend time with us, to see what the construction industry is all about in a practical sense whilst they study.  Some of our work experience candidates haven’t made a final decision on what they want to do and work experience gives them a better idea about the work involved in various areas of the civil engineering and construction industry and gives them a better idea of the direction in which they want to go with their future career path.

We  operate an apprentice training scheme and we are happy to discuss our scheme with those who are dedicated, passionate and have a keen interest in growing and developing themselves within our company.  On average we provide 2 apprenticeship placements each year to support the next generation of construction specialists.

In 2019 we had 4 students who took part in work experience placements and we look forward to welcoming more during 2020.

O’Brien Contractors, Continues to be one of only 9 UK Firms to be Certified FIH Field Builders for Hockey Pitches

O‘Brien Contractors are proud to continue to be one of only 9 certified field builders in the UK for FIH Standard Hockey Pitches and one of only 22 Contractors worldwide to be certified to FIH Field Builder Standards.

FIH Certified Field Builders are companies that specialise in building hockey fields. The companies have a proven ability to construct fields to the standards the game requires. They have appropriate in-house civil engineering expertise for the design and construction of 11-a-side and Hockey 5s fields, operate quality management systems to ensure consistency in their work and provide comprehensive maintenance advice to their customers.

Global Elite Fields: fields that meet the requirements for top level international competitions. Global Elite fields are surfaced with a FIH Global category Approved Hockey Turf.

Global Fields: fields that meet the requirements for international and top level national competitions. Global fields are surfaced with a FIH Global category Approved Hockey Turf.

National Fields: fields that meet the requirements for lower level national, regional and club play. National fields are surfaced with a FIH National or Global category Approved Hockey Turf.

Multi-Sport Fields: fields that allow a number of sports to be played including community and development level hockey. Multi-Sport fields are surfaced with a FIH Multi-Sport, National or Global category Approved Hockey Turf.

The FIH Quality Programme for Hockey Turf ensures: the sustainability, affordability and accessibility of hockey turfs worldwide.
A new hockey field is a major investment and it is therefore important that it meets the expectations of hockey players, associations and clubs.

To help ensure good quality fields are built for all levels of play, from elite level competition to community development, the FIH has developed an internationally recognised quality-assurance programme – the FIH Quality Programme for Hockey Turf. The programme was launched as part of an initiative of the Hockey Revolution – FIH’s ten-year strategy for hockey.

The programme provides consistent and dependable industry standards and ensures the appropriate quality of performance for the intended level of play – whether it is community development, international competition, or anything in between. It protects the investment made by facility owners by ensuring the field meets the expectations of those who will be using it.

The FIH certifies hockey turf preferred suppliers, manufacturers, field builders and fields.

New Takeuchi’s Arrive at O’Brien Contractors!

O’Brien have taken delivery 4 new Takeuchi’s yesterday, with a 5th machine arriving today!

O’Brien have taken delivery of 2 x Takeuchi TB153FR, 5 ton machines and 1 x Takeuchi TB290-2, 9 ton machine, with another 290-2 machine being delivered today.

Over the last 4 years O’Brien has invested over £5Million in new plant.

O’Brien are continually investing in new plant to ensure that we have the most up to date modern plant to carry out our works efficiently.  Having our own expansive plant fleet reduces hire costs, ensures efficient working practices on site, as well as ensuring that we have the most up to date and efficient plant in order to complete our projects.

All machines are fitted with up to date industry standard safety features to ensure the safety of our site teams.

When Nick Drew and Earthmovers Magazine Came to Site…

Credit to: Nick Drew and Earthmovers Magazine for Article and Photos

Digital Digging

Leamington Spa based family run business O’Brien Contractors Ltd have been at the forefront of innovative technology in the construction industry since the company was first formed in 1958 by Tom O’Brien, the father of the current directors Peter & Mick O’Brien who are also joined by fellow director Stuart Chamberlain.

Of course, in recent years technology involving state-of-the-art GPS guidance systems has really taken off and we are seeing a massive uptake in machine guidance set ups. O’Brien Contractors have been embracing the concept since it was first introduced into the UK market and as trailblazers fully understand the benefits that Machine Control (3DMC) systems can offer their business. Managing Engineering Surveyor for O’Brien Contractors Gareth Price said, “3D machine control technology not only makes our sites, or in fact any construction site, operate more efficiently and effectively, but also improves safety for our operatives on the ground and around the machine”.

O’Brien Contractors run a diverse fleet of machines from a wide range of manufacturers with an impressive 29 items of plant already running machine controls systems, these include excavators, dozers and even rollers. The company have always had a strong relationship with Takeuchi, primarily for the products well proven, tried and tested reliability. They have been running the distinctive red and grey Japanese built excavators on the fleet for well over 15 years now ranging from 1.5 tonne class TB216’s and nine tonne class TB290’s right up to the 15 tonne TB2150’s with offset booms. The most recent addition to the fleet is a TB2150R which features a conventional fixed boom which is said to be the first of its kind to be fitted with 3D machine control. Talking about the machine Gareth Price said, “The natural evolution of our relationship with Takeuchi was to marry a Topcon 3DMC system to the new TB2150R, we have looked into fitting the systems to our offset boom versions but that’s still a bit complicated at the moment, but I’m confident a solution will be found, but for now we are happy to have the system on the new fixed boom model”.

We caught up with the new machine on a site in Worcester, where O’Brien’s are tackling the work for Stoford Developments Limited forming part of the next phase of expansion for the Worcester Six Industrial Estate. This work includes but is not limited to 5,600m2 of site strip under an archaeological watching brief, 500m of watercourse diversion, and 1300m of bund construction all involving circa 12,000m3 of earthworks. On the day of our visit the Takeuchi was excavating part of the site for the archaeologists who are performing a survey of the area ahead of the main excavation works and the operator had pre-mapped out the excavation including shelving levels before digging commenced.

At the controls was long term operator John Neeson, who has been driving excavators for over 32 years. Until he joined O’Brien Contractor’s John, like many an old school operator, had never used a machine control system before, but after a few hours of training he is now fully confident in the use and application of the Topcon 3DMC. At the time of our visit John had been using the GPS system for a couple of weeks and he was keen to talk to us about his experience with it so far, John said, “I was sceptical at first, but I have to say that since using the Topcon system for a short period of time, I wouldn’t want to be without it now, it’s just a fantastic piece of kit and from an operators point of view, it just makes my life a lot easier”.

John continued, “As I said previously, I’d never used one before and initially it was a bit daunting, but I have found it very easy to use and of course we are lucky to have a very good engineering back up team on the end of the phone if there are ever any problems. Also, from an ease of use and safety perspective, it means we only require minimal groundcrew around us which is reassuring and it also eliminates the need for any spray paint lines so that’s one more thing less to have to worry about as the dig is all mapped out in the GPS system”. Explaining how the back-up works Gareth Price said, “We can offer John all our other GPS operators full support from the office via our remote support system our Engineering Surveyors to remotely access and control the 3DMC system from any internet-connected device. This support network is invaluable in reducing down time, remotely updating models and offering continued support for our drivers”.

As an example of how easy it is, John said he had arrived in the corner of the green field, and marked out the plan of the dig using the GPS unit, which mapped it all out for him on the screen without him having to leave his cab. Gareth demonstrated how the system can be accessed remotely via a mobile phone or tablet at any time of the day or night, incredible technology! The company operate a policy of one machine, one operator, and his GPS system which is dedicated to that machine for its entire working life on the fleet, when machines are traded-in they are generally sold with the GPS system intact as part of the machine. For security reasons the Topcon screen and receiver pods are easily removed at the end of the shift and can be taken off site for safe keeping overnight. The movement sensors are mounted on the upper-structure, boom, dipper and bucket tipping link and are securely bolted on.

Due to the intricate nature of the works to be carried out on this project shaping the watercourse this site was identified as the ideal application for the Takeuchi excavator combined with the Topcon 3DMC system. Operator John is normally found at the controls of one of O’Brien’s new Caterpillar 320 next generation 20 tonne class excavators, but in the early stages of this job he was trying out the new Takeuchi and had plenty of praise for it saying, “I must say it’s a nice piece of kit, very smooth and precise on the sticks and with plenty of speed and power, it’s a good all-round package really”.

Photo: John Neeson’s regular mount the Caterpillar 320 Next Generation excavator. The machine itself tips the scales at 15.6 tonnes and like its off-set boom style counterpart the TB2150, it retains the German built 4-cylinder Deutz TCD3.6L4 engine which is a Stage 4 Final emissions compliant unit complete with AdBlue system and DOC unit to achieve the required emissions levels. This engine has a rated power output of 85kw (115hp) @2000rpm.

This example was fitted with the standard 700mm UK spec steel triple grouser track pads. The undercarriage has an overall length of 3750mm and measures 2690mm in width which gives the machine a good footprint and offering extremely good balance throughout the working arc. Forward and centrally mounted track guides help to keep everything in place even in the toughest of terrains, and twin speed track motors with auto step down function provide torque on demand when pushing, climbing slopes or when turning in high speed mode.

 

The mono boom features check valves which are located behind the boom lift rams for protection from accidental damage and a check valve is also fitted on the dipper ram. There are 3 x auxiliary hydraulic circuits fitted as standard.

 

The TB2150R is still being rolled out with a relatively short 2.3m dipper arm, but there has since been an upgrade to a new dipper size of 2.85m, not far short of the standard preferred UK spec of 3m. As we understood previously, following consultation between UK dealers and Takeuchi designers in Japan they plan to re-design the dipper and fit a larger top ram to offer the same breakout force as is currently achievable with the shorter dipper. At the business end on this example a Tefra automatic hydraulic quick coupler from Hill Engineering was fitted.

 

Its down to forward thinking companies such as O’Brien Contractors that we are now seeing much more of this GPS kit being used, its only going to be a matter of time before this digital digging technology becomes the industry standard.

 

https://www.earthmoversmagazine.co.uk/digger-man/view,digital-digging_2357.htm

Who’s Been Naughty and Who’s Been Nice on Christmas Jumper Day!!!

Our annual Christmas Jumper and Charity Shoe Box Day has arrived!

So who are the naughty people not wearing a jumper!

Mmm, take a look at the rogues in the gallery of photos to find out!  On the plus side they paid their money for charity (£5 entry fee for the office staff) all money goes to the O’Brien Charitable Trust.

Lots of lovely jumpers around the office and a few head and beard trimmings as well!

The staff also bring in shoe boxes filled with goodies and necessities for the homeless, vulnerable and lonely for ‘Coventry Cyrenians Charity’, who distribute the boxes on Christmas day and provide a Christmas meal for those less fortunate.

MOVEMBER KING OF THE MOUSTACHE WINNER 2019! £1,800 RAISED!

The boys in the office have done us proud once again, raising an amazing £1,800 for the O’Brien Charitable Trust in the Movember Challenge.

Dan Taylor, John Maxwell and James O’Brien grew those top lip warmers for the whole of November (in the freezing weather we have had, they were likely glad of the extra warmth)!

With Peter O’Brien pledging additional money for the winner, we decided to put the vote to the public and let them decide who the winner would be and after a 24 hour vote, the public decided that John Maxwell was the voted King of the Moustache this year, (although they are all winners in our eyes).

John raised £1,130 which is a fantastic amount of money!

Thank you to everyone who sponsored our worthy contestants and got behind one of our last fundraisers of the year, in our quest to raise that magic £15,000.

Just in case you don’t know, if the staff raise £15,000 between January and the end of December, the O’Brien Directors match that amount so we have £30,000 to distribute in January to our chosen Charities for 2019.

We really appreciate all the support and sponsors, not just for this event, but all of our events throughout the year.

WATCH OUT FOR OUR CHRISTMAS JUMPER DAY POST ON 13 DECEMBER!

 

O’Brien Wins Multi Million Pound Contract at Barry Callebaut Chocolate Factory, Banbury

O’Brien have secured a multi million pound contract at the Barry Callebaut factory, Banbury.

O’Brien have been engaged as Principal Contractor for major civils works at the Barry Callebaut chocolate manufacturing site. The project consists of extending and refurbishing an existing chocolate factory to increase production by circa 20%.

Barry Callebaut is the world’s leading manufacturer of high-quality chocolate and cocoa products, and has been dedicated to this business for more than 150 years. The company operates out of more than 40 countries, runs about 60 production facilities, employs a global workforce of more than 12,000 people.  With average sales of 2,139,758 tonnes of chocolate and cocoa products (2018/19), their products are present in one out of four of all chocolate and cocoa products consumed around the world.

Following on from our successful enabling package that we carried out on site earlier this year and a lengthy tender and discussion process we have secured the contract to carry out this major project at the Banbury site.

Works on the project include the construction of a brand new 40m x 13m stand alone Utilies / Energy Centre, as well as major alterations, building extensions and upgrading works to other buildings on the site.  We will also be constructing a new concrete tanker yard and internal access roads as part of the works.

The works are taking place in a live food manufacturing environment with a busy delivery and loading operation, therefore the works are being carefully phased with a control regime to reflect our client’s standards for work within the production facilities on site.

The works have now commenced on site where works will take place over the next 12 months.

O’Brien Charitable Trust – 2019 Events Success Story

CHARITY BALL – WARWICK CASTLE

An amazing night at our sell out charity ball at the beautiful Warwick Castle.

Our suppliers, sponsors and guests were all so generous, making the event a fantastic, fun filled event with over 150 guests, who enjoyed all of the fabulous entertainment on offer as well as a delicious meal in the amazing Great Hall.

Guests enjoyed the hilarious game of Bums & Heads, and whilst our guests enjoyed a slap up three course meal and drinks, they were entertained by the Castle’s feuding Knights battling it out, which was absolutely fabulous and exciting to watch.  This was followed by our silent auction where we had some exciting and very generous donations and very generous bids, followed by the live band so guests could  dance the night away.

We had donations of some fabulous auction items at this year’s ball to bid on, raising over £2,000 which included:

  1. Signed England Rugby Shirt – Kindly Donated by Ben Lewitt at Green Room Sports
  2. Framed James Hakell Signed Help for Heroes Shirt – Kindly Donated by Look Who’s Talking
  3. Signed Aston Villa Shirt – Kindly Donated by Aston Villa Football Club
  4. Half Day Jaguar Land Rover Experience – Kindly Donated by Jaguar Land Rover
  5. Hamper Basket – Kindly Donated by O’Brien Contractors Ltd
  6. Champagne – Kindly Donated by MGP
  7. Four Tickets to Warwick Castle – Kindly Donated by Warwick Castle
  8. Two Tickets to The Arts Theatre London – Kindly Donated by Lizzie Scott
  9. Japan World Rugby Signed Ball – Kindly Donated by Ben Lewitt at Green Room Sports

CHARITY GOLF DAY – WARWICKSHIRE GOLF & COUNTRY CLUB

Another absolutely brilliant day of fun at our annual Charity Golf Day, where despite the weather everyone had a fabulous time and helped the Charitable Trust raise lots of money to help reach our magic goal of £15,000 by December 2019.

A MASSIVE THANK YOU!!

To suppliers, Warwickshire Golf and Country Club, and all other attendees and everyone else who supported the event in any way. Without the support of all the wonderful people that attend, take part in the auctions, donate items etc, we couldn’t raise as much as we do!
THE WINNERS WERE!!! Construction Skills team who won all three categories: The team event, the individual and runner up event.